- Good afternoon,
- Below are the minutes from today’s meeting
- November 3, 2015 - DKM Meeting Minutes - Data Management International
- Tuesday, November 03, 2015
- 1:41 PM
- Attendees:
- 1. PB:
- a. Susan Bobel
- b. Chad C Druck
- c. Darrell Martin (Absent)
- d. Reginald Echeumuna
- e. Jeff Allen
- 2. Data Management International
- a. Dan Carson
- b. Ed Madanat
- Action Items
- 1. (OWNER: Data Management International )
- a. Set up PC
- b. Install TeamViewer on PC
- i. Below is the Teamviewer link that is licensed to Pitney Bowes:
- 1. http://pb.com/remote
- c. Provide Teamviewer Access credentials
- d. Confirm International shipping requirement
- e. Provide SMTP for email notification
- 2. OWNER: (Pitney Bowes)
- a. Provide CRD to remove Batching from SOW. DMI has confirmed the current process is completed manually - Reginald Echeumuna
- b. Provide SRS White papers -Reginald Echeumuna
- c. Provide CSV format requirements -Reginald Echeumuna
- d. Request fast tracking of receipt IOP Keys-S. Bobel
- Meeting Minutes
- 1. Scope:
- 2. Installation Start date November 11, 2015. Darrell Martin to begin base installation.
- 3. Pitney Bowes to provide
- a. Workstation (PC)
- b. Scale
- c. Printer
- 4. Carriers:
- a. USPS
- i. IOP
- 1. Release Date 11/18/2015
- ii. email Notification
- 5. Batch processing to be removed from scope- DMI has confirmed the current process is completed manually
- 6. Manifesting
- 7. IT contact
- a. Dan Carson, (302) 656-1151, dcarson@dmi-inc.com
- 8. Standard Labels
- 9. Standard Reports
- 10. Out of Scope:
- a. Imports
- b. Exports
- c. UPS
- d. FED
- e. DHL
- f. LTL
- g. Custom labels
- h. HazMat shipments
- i. 3rd Party Billing
- j. International shipping
- Project Milestones Status
- Milestone
- Original
- Projected
- Actual
- Pre-Installation
- Tue 11/3/15
- Tue 11/3/15
- PC Available
- Tue 11/3/15
- Tue 11/3/15
- Tue 11/3/15
- Install TeamViewer on PC
- Tue 11/3/15
- Tue 11/3/15
- Tue 11/3/15
- Remote PC Access
- Wed 11/4/15
- Wed 11/4/15
- Provide SMTP for email notification
- Wed 11/4/15
- Wed 11/4/15
- Installation
- Wed 11/11/15
- Wed 11/11/15
- SendSuite Live
- Wed 11/11/15
- Wed 11/11/15
- Base SSL installation
- Wed 11/11/15
- Wed 11/11/15
- Projects setup
- Thu 11/12/15
- Thu 11/12/15
- IOP
- Wed 11/18/15
- Wed 11/18/15
- Submit Manifest to USPS
- Thu 11/19/15
- Thu 11/19/15
- Web Ex
- Thu 11/19/15
- Thu 11/19/15
- Web Ex Review of SSL setup
- Thu 11/19/15
- Thu 11/19/15
- Configure SSL based on Web Ex
- Thu 11/19/15
- Thu 11/19/15
- Training and Go Live
- Thu 11/19/15
- Thu 11/19/15
- Onsite Hardware Setup
- Thu 11/19/15
- Thu 11/19/15
- Customer Training
- Fri 11/20/15
- Fri 11/20/15
- Initial Go Live
- Mon 11/23/15
- Mon 11/23/15
- Go Live Monitoring
- Tue 11/24/15
- Tue 11/24/15
- Sign off
- Wed 11/25/15
- Wed 11/25/15
- Meeting Notes Routing
- Janice D Creevy <Janice.Creevy@pb.com>; Chad C Druck <Chad.Druck@pb.com>; Darrell Martin <darrell.martin@pb.com>; Reginald Echeumuna <reginald.echeumuna@pb.com>; Jeff Allen <jeffrey.allen@pb.com>; Philip L Hatcher <Philip.Hatcher@pb.com>; Timothy Tanner <Timothy.Tanner@pb.com>;'Dan Carson' <DCarson@dmi-inc.com>; emadanat@dmi-inc.com
- Created with Microsoft OneNote 2013.