- [QUOTE="Birkal, post: 8154594, member: 66676"]Gen7 CAP27 Proposed Calendar
- Mid-June - CAP26 is completed
- End of June - Concept Assessment begins
- End of September - CAP27 concludes
- October & November - Two months of playtesting in the final SM meta
- November 18th - Pokemon Sword & Shield Release
- December & January - Policy Review Committee, and enjoying Gen8
- End of February - Sword & Shield meta is calm enough for us to begin CAP28
- [/QUOTE]
- I think what this schedule misses is how End of June to End of September is about 3 months. Here's how long the past CAPs have taken (excluding CAP25, which was longer for obvious reasons):
- CAP26: Feburary 2, 2018 - Mid June, about 4 and a half months
- CAP24: January 30, 2018 - May 17, 2018, a little less than 5 months
- CAP23: July 18, 2017 - November 27, 2018, just over 4 months
- CAP22: June 10, 2016 - October 26, 2018, just over 4 months
- So, what I'm seeing here is that we finish CAPs generally around 4 and a half months. Again, you're proposing 3 months, effectively calling for the process to chop a third of the time somewhere. Could you elaborate on where that time comes from, because that's a rather large chunk of time. Sure, if we have a deadline we could "rush" things, but I'd be interested in knowing what exactly we rush - which threads do we chop off time for? - do we set deadlines for those threads? Or, do we have to eat into playtesting time? If so, how much? If we're going to fit in another CAP into the year, I want to know what our time budget is.