- ⁃ activate all levers (8)
- ⁃ Fuel panel: Reactor operation mode dial: nominal
- ⁃ Fuel panel: Insert in Core (fuel block)
- ⁃ Pressurisation: heaters ON
- ⁃ Pressurisation: check heating power HIGH
- ⁃ Coolant system: dial ordered MEDIUM
- ⁃ Coolant system - circulation pumps: START all the pumps you currently have
- ⁃ Coolant system - all freight pumps: LOAD
- [if restarting, also set core outer vessel dial to LOAD]
- ⁃ Condenser panel - coolant flow speed - ordered dial to FAST, then START condenser
- ⁃ [first time only] While awaiting pressurisation, iPad 75k loan 4 weeks
- ⁃ [first time only] While awaiting pressurisation: iPad buy AO control rods, pressure, maintenance
- ⁃ Pressurisation: await pressure & temperature green
- ⁃ Pressurisation: heating power dial LOW
- [if restarting, check water level is above control rods before proceeding]
- ⁃ Coolant system - all freight pumps: OFF
- [if restarting, also set core outer vessel dial to OFF]
- ⁃ Control rods - keypad: 98 SET
- [will be a lower number in an upgraded plant & as core fuel reduces]
- While awaiting critical reaction: Energy generation - Resistor banks ON, Compensator ON, Turbine bypass 33%
- [if restarting an upgraded plant, increase initial bypass to suit]
- ⁃ Await critical reaction
- ⁃ Steam generators: START all the generators you currently have
- ⁃ Steam generator - coolant flow speed: dial MEDIUM [FAST if restarting upgraded plant]
- ⁃ Pressurisation: heaters OFF
- [if restarting, breaker should be OPEN]
- [if restarting an upgraded plant, monitor generated energy closely and adjust turbine bypass to avoid overloading resistors]
- ⁃ Energy generation - await 150kw [if restarting an upgraded plant, it will require more energy]
- ⁃ Internal or external supply: STOP/OFF
- ⁃ Await reactor temp 250deg
- [will be higher in an upgraded plant, needs to be near green band]
- ⁃ Ipad AO turn on
- ⁃ iPad AO activate control rods & pressure functions
- ⁃ iPad request start operation
- ⁃ Await operation start time
- ⁃ Synchroscope: raise and lower speed (blue panel) to center dot
- ⁃ Circuit breaker CLOSE when holding synchronised (sync is shown as two green dots on synchroscope)
- ⁃ Synchroscope: increase/decrease voltage (green panel) to match grid
- ⁃ Turbine bypass 0 when feeding grid
- [if restarting an upgraded plant, monitor generated energy closely and adjust turbine bypass to avoid over-revving turbine]