  1. QUESTION NO: 1
  2.  
  3. An element of the project scope statement is:
  4.  
  5. A.
  6. Acceptance criteria.
  7.  
  8. B.
  9. A stakeholder list.
  10.  
  11. C.
  12. A summary budget,
  13.  
  14. D.
  15. High-level risks.
  16.  
  17.  
  18. Answer: A
  19.  
  20.  
  21.  
  22.  
  23. QUESTION NO: 2
  24.  
  25. Which document describes the necessary information to determine if a project is worth the required investment?
  26.  
  27. A.
  28. Cost baseline
  29.  
  30. B.
  31. Service level agreement
  32.  
  33. C.
  34. Memorandum of understanding
  35.  
  36. D.
  37. Business case
  38.  
  39.  
  40. Answer: D
  41.  
  42.  
  43.  
  44. QUESTION NO: 3
  45.  
  46.  
  47. Which input to the Plan Risk Management process provides information on high-level risks?
  48.  
  49. A.
  50. Project charter
  51.  
  52. B.
  53. Enterprise environmental factors
  54.  
  55. C.
  56. Stakeholder register
  57.  
  58. D.
  59. Organizational process assets
  60.  
  61.  
  62. Answer: A
  63.  
  64.  
  65.  
  66.  
  67. QUESTION NO: 4
  68.  
  69. Which item is an example of personnel assessment?
  70.  
  71. A.
  72. Resource calendar
  73.  
  74. B.
  75. Tight matrix
  76.  
  77. C.
  78. Team-building activity
  79.  
  80. D.
  81. Focus group
  82.  
  83.  
  84. Answer: D
  85.  
  86. QUESTION NO: 5
  87.  
  88. Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
  89.  
  90. A.
  91. Feedback analysis
  92.  
  93. B.
  94. Stakeholder analysis
  95.  
  96. C.
  97. Communication management plan
  98.  
  99. D.
  100. Stakeholder management plan
  101.  
  102.  
  103. Answer: D
  104.  
  105.  
  106.  
  107.  
  108. QUESTION NO: 6
  109.  
  110. Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
  111.  
  112. A.
  113. Procurement documents
  114.  
  115. B.
  116. Communications plan
  117.  
  118. C.
  119. Project charter
  120.  
  121. D.
  122. Stakeholder register
  123.  
  124.  
  125. Answer: C
  126. QUESTION NO: 7
  127.  
  128. The Identify Stakeholders process is found in which Process Group?
  129.  
  130. A.
  131. Initiating
  132.  
  133. B.
  134. Monitoring and Controlling
  135.  
  136. C.
  137. Planning
  138.  
  139. D.
  140. Executing
  141.  
  142.  
  143. Answer: A
  144.  
  145.  
  146.  
  147.  
  148. QUESTION NO: 8
  149.  
  150. An input to Develop Project Charter is a/an:
  151.  
  152. A.
  153. Business case.
  154.  
  155. B.
  156. Activity list.
  157.  
  158. C.
  159. Project management plan.
  160.  
  161. D.
  162. Cost forecast.
  163.  
  164.  
  165. Answer: A
  166.  
  167.  
  168.  
  169.  
  170. QUESTION NO: 9
  171. Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?
  172.  
  173. A.
  174. Project Risk Management
  175.  
  176. B.
  177. Project Human Resource Management
  178.  
  179. C.
  180. Project Scope Management
  181.  
  182. D.
  183. Project Stakeholder Management
  184.  
  185.  
  186. Answer: D
  187.  
  188.  
  189.  
  190.  
  191. QUESTION NO: 10
  192.  
  193. Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
  194.  
  195. A.
  196. Stakeholder register
  197.  
  198. B.
  199. Scope management plan
  200.  
  201. C.
  202. Stakeholder management plan
  203.  
  204. D.
  205. Project charter
  206.  
  207.  
  208. Answer: A