- QUESTION NO: 1
- An element of the project scope statement is:
- A.
- Acceptance criteria.
- B.
- A stakeholder list.
- C.
- A summary budget,
- D.
- High-level risks.
- Answer: A
- QUESTION NO: 2
- Which document describes the necessary information to determine if a project is worth the required investment?
- A.
- Cost baseline
- B.
- Service level agreement
- C.
- Memorandum of understanding
- D.
- Business case
- Answer: D
- QUESTION NO: 3
- Which input to the Plan Risk Management process provides information on high-level risks?
- A.
- Project charter
- B.
- Enterprise environmental factors
- C.
- Stakeholder register
- D.
- Organizational process assets
- Answer: A
- QUESTION NO: 4
- Which item is an example of personnel assessment?
- A.
- Resource calendar
- B.
- Tight matrix
- C.
- Team-building activity
- D.
- Focus group
- Answer: D
- QUESTION NO: 5
- Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
- A.
- Feedback analysis
- B.
- Stakeholder analysis
- C.
- Communication management plan
- D.
- Stakeholder management plan
- Answer: D
- QUESTION NO: 6
- Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
- A.
- Procurement documents
- B.
- Communications plan
- C.
- Project charter
- D.
- Stakeholder register
- Answer: C
- QUESTION NO: 7
- The Identify Stakeholders process is found in which Process Group?
- A.
- Initiating
- B.
- Monitoring and Controlling
- C.
- Planning
- D.
- Executing
- Answer: A
- QUESTION NO: 8
- An input to Develop Project Charter is a/an:
- A.
- Business case.
- B.
- Activity list.
- C.
- Project management plan.
- D.
- Cost forecast.
- Answer: A
- QUESTION NO: 9
- Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?
- A.
- Project Risk Management
- B.
- Project Human Resource Management
- C.
- Project Scope Management
- D.
- Project Stakeholder Management
- Answer: D
- QUESTION NO: 10
- Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
- A.
- Stakeholder register
- B.
- Scope management plan
- C.
- Stakeholder management plan
- D.
- Project charter
- Answer: A