  1. Purpose
  2. The purpose of the team is to create a student management website to manage students more systematically where students can login, add and edit their details.
  3.  
  4. 2. Background
  5. The college wants a website to manage students more systematically.
  6. The basic users are the students themselves, teachers and shareholders. The project budget is $50,000 and the expected cost is $46,520.
  7. 3. Scope
  8. Mission: Create a student management website to manage students more systematically, with some deliverables – Design, Database, Actual Website and Work Breakdown structure.
  9. Objective:
  10. 1. The security level of the website should be enhanced.
  11. 2. Debugging check should be done to create an error free system.
  12. 3. Website should be minimal to reduce delays.
  13. 4. Team composition
  14. Project Manager – Full time / Internal – 6 weeks – 40 hrs
  15. DB specialist - Part time / Internal – 6 weeks – 20 hrs
  16. DB assistant - Part time / Internal – 6 weeks – 20 hrs
  17. CSS Specialist - Part time / Internal – 6 weeks – 40 hrs
  18. Business Analyst and supporting officer - Full time / Internal – 6 weeks – 40 hrs
  19. 5. Membership roles
  20. Role Name Organization Email Phone number
  21. Project Manager Shailesh Bhandari Verisk sbkk@gmail.com 0428903642
  22. Programmer Shristhi Shrestha Verisk Shristhis@gmail.com 0487659872
  23. Programmer Pujan Karki Verisk pujk@gmail.com 0467509732
  24. DB Specialist Cisam Thapa Deerwalk cisam@gmail.com 0498735263
  25. DB Assistant Abhiman Basnet Verisk abhiman@gmail.com 0487263540
  26. CSS specialist Light Yagami Deerwalk Yagami22@gmail.com 0485632510
  27. Business Analyst Bhupal Rana Deerwalk ranabhupal@gmail.com 0475263012
  28. Supporting officer Jyapu Shrestha Deerwalk Js200@gmail.com 0497550932
  29.  
  30. 6. Team performance assessment
  31. There will be a meeting every Monday morning to check the progress. The progress will be reported to Project Manager every Friday.
  32. 7. Acquisition milestones and schedules
  33. Week 1: Discuss and set concept and complete content creation
  34. Week 2: Build database and complete web development
  35. Week 3 – 4: All the necessary coding and design
  36. Week 5: Debug and check if any errors.
  37. Week 6: Finally Commercialize and complete the project.
  38. 10. Signature page
  39. Role Person/s Signature
  40. Project Manager Shailesh Bhandari
  41. Business Analyst Nishant Thapa
  42. Programmer 1 Shristhi Shrestha
  43. Programmer 2 Pujan Karki
  44. DB specialist Cisam Thapa
  45. DB assistant Abhiman Basnet
  46. Business Analyst Bhupal Rana
  47. Supporting officer Jyapu Shrestha
  48. CSS Specialist Light Yagami