- Purpose
- The purpose of the team is to create a student management website to manage students more systematically where students can login, add and edit their details.
- 2. Background
- The college wants a website to manage students more systematically.
- The basic users are the students themselves, teachers and shareholders. The project budget is $50,000 and the expected cost is $46,520.
- 3. Scope
- Mission: Create a student management website to manage students more systematically, with some deliverables – Design, Database, Actual Website and Work Breakdown structure.
- Objective:
- 1. The security level of the website should be enhanced.
- 2. Debugging check should be done to create an error free system.
- 3. Website should be minimal to reduce delays.
- 4. Team composition
- Project Manager – Full time / Internal – 6 weeks – 40 hrs
- DB specialist - Part time / Internal – 6 weeks – 20 hrs
- DB assistant - Part time / Internal – 6 weeks – 20 hrs
- CSS Specialist - Part time / Internal – 6 weeks – 40 hrs
- Business Analyst and supporting officer - Full time / Internal – 6 weeks – 40 hrs
- 5. Membership roles
- Role Name Organization Email Phone number
- Project Manager Shailesh Bhandari Verisk sbkk@gmail.com 0428903642
- Programmer Shristhi Shrestha Verisk Shristhis@gmail.com 0487659872
- Programmer Pujan Karki Verisk pujk@gmail.com 0467509732
- DB Specialist Cisam Thapa Deerwalk cisam@gmail.com 0498735263
- DB Assistant Abhiman Basnet Verisk abhiman@gmail.com 0487263540
- CSS specialist Light Yagami Deerwalk Yagami22@gmail.com 0485632510
- Business Analyst Bhupal Rana Deerwalk ranabhupal@gmail.com 0475263012
- Supporting officer Jyapu Shrestha Deerwalk Js200@gmail.com 0497550932
- 6. Team performance assessment
- There will be a meeting every Monday morning to check the progress. The progress will be reported to Project Manager every Friday.
- 7. Acquisition milestones and schedules
- Week 1: Discuss and set concept and complete content creation
- Week 2: Build database and complete web development
- Week 3 – 4: All the necessary coding and design
- Week 5: Debug and check if any errors.
- Week 6: Finally Commercialize and complete the project.
- 10. Signature page
- Role Person/s Signature
- Project Manager Shailesh Bhandari
- Business Analyst Nishant Thapa
- Programmer 1 Shristhi Shrestha
- Programmer 2 Pujan Karki
- DB specialist Cisam Thapa
- DB assistant Abhiman Basnet
- Business Analyst Bhupal Rana
- Supporting officer Jyapu Shrestha
- CSS Specialist Light Yagami
Advertisement
Add Comment
Please, Sign In to add comment
Advertisement