Advertisement
Guest User

Untitled

a guest
Jun 24th, 2019
77
0
Never
Not a member of Pastebin yet? Sign Up, it unlocks many cool features!
text 0.44 KB | None | 0 0
  1. 90 "Banheiros"(3 Peças de 1.5mx1m por quarto)
  2.  
  3. 5M tabica = 156Tabicas 1560,00
  4. 8.8 pregos = 800 Pregos de aço 64,00
  5. 1+1/2 f530 = 140 F530 1288,00
  6. 75 placas 1.5x90/2.16+~15% 2137,5
  7. 30 parafusos = 2700 Parafusos 156,00
  8. 3 rolos fita tape 63,00
  9.  
  10. Total Material "Banheiros"
  11. 5,268.5 R$
  12.  
  13. Mão de obra
  14. 1.5 x 1 = 1.5m2. x 25R$ = 37.5R$
  15. 37.5 x 90 = 3375,00R$
  16.  
  17. Total tudo =
  18. 5,268.5 R$ Material +
  19. 3375,00R$Mão de Obra
  20.  
  21. = 8,643.5R$